| 
 
  
    | Problem 2: Operational 
analysis of the I-87/Alternate Route 7 Interchange 
 Printable Version This problem focuses on the interchange 
complex on the western end of Alternate Route 7. Three interchanges are 
intertwined: I-87 and Alternate Route 7, I-87 and State Route 2, and Alternate Route 7 and U.S. 9. Click the thumbnails 
of
Exhibit 4-17 and
Exhibit 4-18 for a visual introduction to this problem. Before proceeding with this problem, we first provide more details on the 
    interchange geometry below. The interchange between I-87 and Alternate Route 7 is a 
classic trumpet with the semi-direct ramp linking Alternate Route 7 west to I-87 
south. Locally, it’s called Exit 7, as noted in
Exhibit 4-18. The one nuance worth 
noting is that the right-hand ramp from Alternate Route 7 west to I-87 north 
leaves Alternate Route 7 east of 
U.S. 9 and 
follows a fairly long path on its way to I-87 north.  The  Alternate Route 7/U.S. 9 interchange is a 
partial-cloverleaf. The connections to Alternate Route 7 east are on the eastern 
side of U.S. 9 while the connections to Alternate Route 7 west are on the 
western side. An extra ramp is needed to provide the connections, because the 
right-hand ramp from Alternate Route 7 to I-87 starts east of the bridge under 
U.S. 9, before the ramps from U.S. 9 connect to Alternate Route 7. Consequently, 
to provide connection from U.S. 9 via Alternate Route 7 to I-87, an extra ramp 
diverges from the U.S. 9 on-ramp north of NYS-7 and connects directly to the 
right-hand ramp from Alternate Route 7 west to I-87 north.  The interchange between I-87 and State Route 2, Exit 6, is a simple diamond. 
It’s called Exit 6 as labeled in the diagram. Getting to it coming southbound is 
a bit complex. That needs a short discussion.   [ 
    Back 
    ] to Problem 1 [ Continue ] 
    with Problem 2 |  
    Page Break
  
  
    |  |  
      | I-87/Alternate Route 7 Interchange (Note: Move the cursor over this aerial photograph 
to find hotspots that will allow you to see more detail of the interchange with 
a ground level photograph. The hotspots are highlighted by a dashed line 
rectangle in the figure below.) Starting at the top of the image and working 
south, we see the following things. First there are the exit ramps to Exits 6 
and 7. The sliver of white is the gore that separates the two exit ramp lanes 
from the three main lanes. Next is the loop ramp to NYS-7 east. Then you can see 
the short single-lane connector that takes traffic going south to Exit 6 go from 
the diverge with the loop ramp to the merger with the semi-direct ramp.  Starting at the southern end of the picture and working 
      north, you can see Sparrowbush Road that crosses over the weaving section 
      just north of Exit 6. Then you can see the point where the right-hand ramp 
      diverges to NYS-7 east. To the right you can then see the interchange 
      between NYS-7 and U.S. 9. On the south side of NYS-7 are the ramps to and 
      from the eastbound direction. On the north side are the ramps to and from 
      westbound direction. Also visible is the ramp short connector we described 
      earlier that allows a connection from U.S. 9 to I-87 northbound. Click
      here 
      to see an aerial photograph with key locations noted. |  
      |  |  
      |  |    
  
    Page Break
  
  
    |  |  
      | 
      Exhibit 4-18. Interchange sketch. The six dashed-line rectangles in the figure 
below are hotspots.  Click 
in these boxes to see a more detailed ground level photograph of that area of the 
interchange. |  
      |  |  
      |  |    
  
    Page Break
  
    | 
    Problem 2: Operational analysis of the I-87/Alternate Route 7 Interchange Looking again at
Exhibit 4-18, you can see that all southbound vehicles wanting either Exit 6 or Exit 7 have 
to leave I-87 at the top of the diagram. Those going to Alternate Route 7 east diverge where the loop ramp turns west. Those going to Exit 6 
continue south. Vehicles coming south 
from I-87 toward Exit 6 weave through the vehicles from the semi-direct 
ramp to I-87 south. A high percentage of vehicles on 
the semi-direct ramp have to cross the 
I-87 traffic going to Exit 6  then use the single lane  slip ramp south of Location C to get to I-87.  This 
difficult weave is one of the places analyzed in this problem.  Now that you know  some important details on the geometry of 
the interchange, let's consider the problem at hand, the completion of an operational 
analysis of the interchange. We will consider two specific 
procedures from the HCM, one to analyze weaving sections and the other to 
analyze ramp junctions. We will illustrate these two procedures using the four 
sub-problems listed below. 
        Sub-problem 2a. What 
types of analysis should be conducted on the I-87/Alternate Route 7 interchange?Sub-problem 2b. What are the 
levels of service in the weaving sections located in the I-87/Alternate Route 7 interchange? These sections are 
        noted as points A, B, and C in the interchange sketch.
 Sub-problem 2c.What are 
the levels of service along the ramp and at the ramp junction for the on-ramp 
from Alternate Route 7 to I-87 northbound? 
This section is noted as point D in the intersection sketch.
 Sub-problem 2d. 
What is the effect of making 
        geometric improvements to the 
        ramp and at the ramp junction for the on-ramp from Alternate Route 7 to I-87 
    northbound?
  [
    Back ] [ Continue ] to 
    Sub-problem 2a |  
    Page Break
  
    | Sub-problem 2a: What 
    types of analysis should be conducted on the I-87/Alternate Route 7 interchange? Step 1. Setup We first need to determine the types of analysis that we 
    will conduct on the I-87/Alternate Route 
    7 interchange. We know from the HCM 2000 that there are four facility 
    types: a basic freeway segment, a ramp junction, a weaving section, and a 
    freeway facility (in which the three previous types are integrated together 
    into a facility). One of the common challenges in a traffic analysis 
    is to match the geometry found in a real problem with the four facility 
    types described in the HCM. It is useful as we start this problem to 
    determine which types of facilities are present in this interchange as we 
    have defined it. 
    Exhibit 
    4-19 shows the interchange, both with a base map showing the named 
    roadway segments and a schematic showing how the road segments intersect. 
    Each of the schematic links is on the mainline of the freeway, a connector 
    roadway, or a ramp. Study the map to better familiarize yourself with the 
    components of the interchange. 
    Discussion:
  Consider the information presented in the 
    figure above showing the various elements of the I-87/State Road 7 
    interchange. If necessary, go back to the previous pages and study the 
    Exhibits presented on these pages. After reviewing this 
    information, list the segments that you think should be analyzed and 
    identify what facility types they represent. When you are ready, proceed to the 
    next page. 
    [Back] to Problem 2 [
    
    Continue 
    ] with Sub-Problem 2a  |  
    
    Page Break
  
    
      |  |  
      | I-87/Alternate Route 7 Interchange. 
     |      
    
    Page Break
  
    | Sub-problem 2a: What 
    types of analysis should be conducted on the I-87/Alternate Route 7 interchange? Step 2. Results The I-87/Alternate Route 7 interchange is  
    complex. To evaluate the operations of this interchange, we 
    need to break it down into several components, either weaving sections or 
    ramp junctions. A weaving section is a segment of an 
    uninterrupted flow facility (often a freeway) that requires a 
    high proportion of vehicles  to change lanes to reach their desired 
    locations on the freeway. A weaving section is further characterized by the 
    number of lanes in the weaving section, the length of the section, the 
    number of lane changes required of the weaving traffic, and the type of 
    terrain or grade. A ramp junction is the 
    intersection of an on-ramp or off-ramp with a freeway, a point at which 
    traffic either merges onto the freeway or diverges from the freeway. Similar 
    to a weaving 
    section, there is a higher degree of turbulence in the traffic stream near a 
    ramp than in sections of the freeway that are longer distances away from a 
    ramp or interchange. While an on-ramp at 
    the beginning of a weaving section or an off-ramp at the end of a 
    weaving section can also be analyzed as a ramp junction, the traffic stream 
    characteristics present in a weaving section are more complex than would be 
    present at a ramp junction alone. Thus, a separate procedure is needed 
    to properly evaluate the effects of this higher degree of turbulence in the 
    traffic stream. 
    [Back] 
    [Continue] 
    with Sub-Problem 
    2a |  
    
    Page Break
  
    | Sub-problem 2a: What 
    types of analysis should be conducted on the I-87/Alternate Route 7 interchange? Let's first list the ramp junctions present in the 
    interchange. From
    
    Exhibit 4-19, we can see there are a total of sixteen ramps in our 
    current study area: 
      
      westbound 
      Alternate 
      Route 7 exit ramp to I-87 northbound
      westbound Alternate Route 7 exit 
      ramp to U.S. 9
      westbound Alternate Route 7 
      entrance ramp from U.S. 9
      eastbound Alternate Route 7 
      entrance ramp from I-87 northbound
      eastbound Alternate Route 7 exit 
      ramp to U.S. 9
      eastbound Alternate Route 7 
      entrance ramp from Alternate Route 7
      southbound I-87 exit ramp to 
      frontage road
      southbound I-87 frontage road 
      exit ramp to Alternate Route 7
      southbound I-87 frontage road 
      entrance ramp from Alternate Route 7
      southbound I-87 frontage road 
      exit to I-87 southbound mainline
      southbound I-87 entrance ramp 
      from southbound I-87 frontage road
      northbound I-87 entrance ramp 
      from State Route 2 and 7
      northbound I-87 exit ramp to 
      eastbound Alternate Route 7
      northbound I-87 entrance ramp 
      from westbound Alternate Route 7
      entrance ramp on I-87 entrance 
      ramp from U.S. 9
      entrance ramp from U.S. 9 to 
      westbound Alternate Route 7 ramp However, only three of the locations represent true 
    freeway merge or diverge points: 
        
        westbound Alternate Route 7 
        exit ramp to I-87 northbound (including both a diverge point from Alternate Route 7 and 
        a merge 
        point onto I-87)
        eastbound Alternate Route 7 
        on-ramp from U.S. 9 (this is a merge point)
        southbound I-87 entrance ramp 
        from southbound I-87 frontage road (this is also a merge point) [
    Back ] [ 
    Continue ] with Sub-Problem 2a  |  
    
    Page Break
  
    | Sub-problem 2a: What 
    types of analysis should be conducted on the I-87/Alternate Route 7 interchange? These points can be analyzed using 
    HCM Chapter 25. The other points can also be evaluated to determine the adequacy 
    of their capacity, but the HCM procedures do not apply to the merge 
    operations at these points. Note that the other merge and diverge 
    points on the freeway segments that constitute this interchange are part of 
    weaving sections and are discussed below. Let's now consider the weaving sections. They are 
      composed of these on- and off-ramps that are no longer than 2,500 feet 
      apart, or slightly less than one-half mile. If the ramps are spaced 
      more than 2,500 feet apart, the turbulence resulting from the lane changing 
      is limited to the vicinity of the ramps themselves, rather than being the combined 
      effect of the on and off-ramps. 
    There are three weaving sections in this interchange: 
      
      northbound I-87 
      between the entrance ramp from State Route 2 and 7 to the exit ramp to 
      eastbound Alternate Route 7
      southbound I-87 
      between the frontage road entrance ramp from Alternate Route 7 to the I-87 
      southbound mainline
      eastbound 
      Alternate 
      Route 7 between the entrance ramp from I-87 northbound and the exit ramp 
      to U.S. 9 In order to assess the overall operation of the 
        interchange, with its four ramp junctions and three weaving sections, 
        we would need to evaluate the level of service at each one. However, in the interest of time,  we will limit our focus here to the three weaving sections and 
        one ramp junction. When you are ready, proceed 
    to Sub-problem 2b. [
    Back ] [
    Continue ] to Sub-Problem 
    2b |  
    
    Page Break
  
    | Sub-problem 
    2b: What are the Levels of Service 
    in the Weaving Sections Located in the I-87/Alternate Route 7 Interchange? Step 1. Setup 
        In this sub-problem, we will consider the three weaving 
        sections that are part of the I-87/Alternate Route 7 
        interchange and determine the quality of service that is provided to 
        drivers traveling through these sections. These  weaving sections, shown 
        in Exhibits 4-20, 4-21, and 4-22,  are classified as Type A 
        weaves. 
As we begin this sub-problem, consider these questions: 
      |  | What type of analysis will produce an evaluation of 
      traffic conditions present at the weaving sections? |  |  | What data are needed to analyze the operations of these 
      weaving sections? |  |  | What are the limitations of the models used to analyze 
      the performance of a weaving section? |  |  | Why are these weaving sections considered to be Type A 
      weaves? |  |  | What measures of effectiveness are used to evaluate the 
      performance of a weaving section? |  |  | What is meant by the terms "constrained operation" and 
      "unconstrained operation?" |  Discussion:
  Take a few minutes to consider 
    these questions. When you are ready, continue to the next page. 
    [ 
    
    Back 
    ] [ 
    
    Continue 
    ] with Sub-Problem 2b  |  
    
    Page Break
  
  
    
      |  |  
      | Exhibit 4-20. Weave A 
The beginning point of
Weave A is defined by two entrance ramps to Alternate Route 7 eastbound, one from 
the circular loop ramp from I-87 southbound and one from the direct ramp from 
I-87 northbound. The end point of the weave section is defined by the point 
where the exit ramp to U.S. Route 9 leaves the EB Alternate Route 7 mainline. 
Weave A is a Type A weave. Why? In a Type A weave, both of the weaving traffic 
streams must change lanes once in order to reach their desired destination. 
Let's consider how this applies to Weave A. Traffic on the circular loop ramp 
from I-87 southbound desiring to travel to U.S. Route 9 must cross the crown 
line to reach this exit, and thus change lanes once. Similarly, traffic from the 
northbound I-87 exit ramp desiring to stay on Alternate Route 7 must change lanes once in order to 
be in the two left most lanes, the mainline for Alternate Route 7. The 
crossing of these two streams produces the turbulence that defines a weaving 
section. 
Local traffic engineers have estimated that 
30 percent of the traffic entering the section is weaving, while 70 percent is 
through traffic or is not weaving. 
       |      
    
    Page Break
  
  
    
      |  |  
      | 
Exhibit 4-21. Weave B 
Weave B is located on I-87 northbound between the on-ramp from State Routes 2 
and 7 on the lower left of the figure below (known locally as entrance 6) and 
the exit to Alternate Route 7 (known as exit 
7). 
Weave B is a Type A weave. Why? Here, both weaving streams must change lanes 
once in order to reach their final destination. Traffic entering from State 
Routes 2 and 7 (entrance 6) must change lanes once in order to stay on the 
mainline I-87 northbound. Traffic on I-87 northbound desiring to travel to 
Alternate Route 7 eastbound must 
change lanes once to reach this off-ramp. 
Studies by local traffic engineers indicate that virtually no traffic entering 
from State Routes 2 and 7 also exit to Alternate Route 7 eastbound. They also 
estimate that 60 percent of the I-87 northbound traffic desires to exit to 
Alternate Route 7 eastbound, with the 
remaining 40 percent continuing on I-87 north past exit 7. 
       |      
    
    Page Break
  
  
    
      |  |  
      | 
Exhibit 4-22. Weave C 
Weave C is formed by the I-87 southbound frontage road and the semi-direct ramp 
from westbound Alternate Route 7. The 
I-87 southbound frontage road and the slip ramp back to the I-87 mainline form 
the southern boundary of the weaving section. 
Weave C is a Type A weave. Why? In a Type A weave, both of the weaving traffic 
streams must change lanes once in order to reach their desired destination. 
Let's consider how this applies to Weave A. Traffic on the circular loop ramp 
from I-87 southbound desiring to travel to U.S. Route 9 must cross the crown 
line to reach this exit, and thus change lanes once. Similarly, traffic from the 
northbound I-87 exit ramp desiring to stay on Alternate Route 7 must change 
lanes once in order to be in the two left most lanes, the mainline for Alternate Route 7. The 
crossing of these two streams produces the turbulence that defines a weaving 
section. 
Local traffic engineers have estimated that 
30 percent of the traffic entering the section is weaving, while 70 percent is 
through traffic or is not weaving. 
       |      
    
    Page Break
  
    | Sub-problem 
    2b: What are the Levels of Service 
    in the Weaving Sections Located in the I-87/Alternate Route 7 Interchange? Now let's review each of these questions and discuss why they are 
    relevant to this analysis. 
What type of analysis will produce an evaluation of traffic 
conditions present at the weaving sections? The 
Highway 
Capacity Manual (HCM) includes two 
kinds of analysis, depending on the problem that the analyst is attempting to 
address. An operational analysis produces an estimate of level of service, 
based on a detailed analysis of existing or projected traffic, geometric, and 
control conditions. A design analysis produces a value of a geometric 
parameter that will produce a given level of service. Here we will focus 
on an operational analysis of the weaving section. 
What data are needed to analyze the operations of these 
weaving sections? The weaving analysis procedure, documented 
    in Chapter 24 of the HCM, requires the following input data: 
      |  | the freeway free-flow speed |  |  | the number of lanes in the weaving section |  |  | the length of the weaving section |  |  | the terrain topography (level or rolling) |  |  | the configuration (type) of the weaving section |  |  | the weaving volumes |  |  | the 
      peak hour factor |  |  | the percentage of heavy vehicles present in the traffic 
      stream |  
     [ 
    
    Back ] [ 
    
    Continue 
    ] with Sub-Problem 2b  |  
    
    Page Break
  
    | Sub-problem 
    2b: What are the Levels of Service 
    in the Weaving Sections Located in the I-87/Alternate Route 7 Interchange? 
What are the limitations of the models used to analyze the 
performance of a weaving section? The weaving analysis procedure consists of 
five models or algorithms. Each of the models was developed and calibrated from 
several data sets collected from actual freeway operations. It is important when 
applying these sub-models to make sure the data that you are using 
fall within the following limits, which also define the limitations of the data 
sets upon which the models are based:  
      |  | The weaving flow rate, Vw, or the total 
      weaving volume in the section, must be less than 2,800 pc/hr for Type A 
      weaves, for example. |  |  | The flow rate through the weaving section must be less 
      than that allowable for a basic freeway segment. |  |  | The volume ratio, VR, or the proportion of the total 
      flow that is weaving, must be less than 0.45 for a three-lane section and 
      0.35 for a four-lane section.  |  |  | The total length of the weaving section must be less 
      than 2,500 feet, or the section should be considered only as unconnected 
      merge and diverge (ramp junctions) points. |  
If your data are outside of these limits, it may imply 
that poor operations will result and that local queuing should be expected. 
Why are these weaving sections considered to be Type A weaves? The weaving section type is based on the number of lane 
changes that each of the 
weaving traffic streams must make in order to reach their final destination. In both of the cases here, 
each weaving traffic stream must make one lane 
change to reach its desired destination. For more discussion of 
the nature of the weaving traffic in the segments we are evaluating, refer to
Exhibit 4-20 
(Weave A),
Exhibit 4-21, 
(Weave B),  and
Exhibit 4-22 
(Weave C). 
What measures of effectiveness are used to evaluate the 
performance of a weaving section? Typically, the weaving analysis procedure is used to 
    determine the level of service of the section, the number of lanes required 
    to meet a specified level of service, the required length of the weaving 
    section to meet a given level of service, or the type of weaving section 
    configuration required to meet a given level of service. An 
    operational analysis will produce the level of service, while a design 
    analysis can be used to produce the other three outputs. For a weaving 
section, the level of service is defined by the traffic
density. 
What is meant by the terms "constrained operation" and 
"unconstrained operation?" The determination of whether a particular 
    weaving segment is operating in an unconstrained or constrained state is 
    based on the comparison of two variables: the number of lanes that must be 
    used by weaving vehicles to achieve equilibrium or unconstrained operation (Nw) 
    and the maximum number of lanes that can be used by weaving vehicles for a 
    given configuration (Nwmax).  [ 
    Back ] [ Continue ] with 
    Sub-problem 2b  |  
    
    Page Break
  
    | Sub-problem 
    2b: What are the Levels of Service 
    in the Weaving Sections Located in the I-87/Alternate Route 7 Interchange? The New York State Department of Transportation has a 
    program of continuous traffic counting for most freeways and highways in the 
    state. Data gathered from the permanent count stations located on the 
    interchange were used to identify the morning and afternoon peak hour for 
    the entry and exit points at the weaving sections, identified as points A, 
    B, C, and D in Exhibits 4-24, 4-25, and 4-26 below. From these entry and exit counts, 
    local traffic engineers estimated the origins and destinations for the 
    weaving sections based on their knowledge of local traffic flow conditions. Sometimes you will have actual origin-destination movements for a weaving 
    section, but other times, as for this sub-problem, you will need to estimate 
    the weaving flows based on your knowledge of local conditions. Exhibit 4-23 shows the origin and destination data that 
    were estimated for the three weaving sections. 
      
      
      
        | Exhibit 4-23. NYSDOT Origin and Destination Data |  
        | VolumeFROM/TO | vAC | vAD | vBC | vBD |  
        | Weave A - AM peak | 415 | 178 | 336 | 783 |  
        | Weave A - PM peak | 321 | 138 | 520 | 1,212 |  
        | Weave B - AM peak | 658 | 987 | 551 | 0 |  
        | Weave B - PM peak | 1,752 | 2,629 | 1,066 | 0 |  
        | Weave C - AM peak | 0 | 2,420 | 1,150 | 1,150 |  
        | Weave 
        C - PM peak | 0 | 1,067 | 825 | 825 |    
    [ 
    
    Back 
    ] [ 
    
    Continue 
    ] with Sub-Problem 2b  |  
    
    Page Break
  
  
    
      |  |  
      | Exhibit 4-24. Weave A 
         |      
    
    Page Break
  
  
    
      |  |  
      | Exhibit 4-25. Weave B 
           |      
    
    Page Break
  
  
    
      |  |  
      | Exhibit 4-26. Weave C 
             |      
    
    Page Break
  
    | Sub-problem 
    2b: What are the Levels of Service 
    in the Weaving Sections Located in the I-87/Alternate Route 7 Interchange? In addition to the volume data, we must also consider 
    several other input data.  For Weave A, the peak hour factor is used to account for 
    the variation in the traffic flow during the peak hour. Based on 
    previous studies, we will use a peak hour factor of 0.90. The free 
    flow speed was estimated to be 55 (see
    
    previous discussion) mph while the proportion heavy vehicles 
    is assumed to be zero for this analysis. We are also assuming the 
    driver population adjustment factor to be 1.0. What about the geometric data? We've already 
    determined that this is a Type A weave, according to the guidelines of the HCM. We also know from an examination of the aerial photographs 
    and the schematics we reviewed earlier that there are four lanes in 
    the weaving segment, two from each of the entry sections, and two going to 
    each of the two exit sections. The length of the weaving section is 
    1,320 feet, or one-quarter mile. Weaves B and C are also Type A weaves. The input 
    data for these weaving sections, as well as for Weave A, are summarized in 
    Exhibit 4-27. 
      
      
      
        | Exhibit 4-27. Weave Data |  
        |  | Weave A | Weave B | Weave C |  
        | Peak hour factor | 0.90 | 0.90 | 0.90 |  
        | Free flow speed (mi/hr) | 55 | 55 | 55 |  
        | Proportion of heavy vehicles | 0 | 0 | 0 |  
        | Driver population adjustment factor | 1.0 | 1.0 | 1.0 |  
        | Type | A | A | A |  
        | Number of lanes | 4 | 5 | 3 |  
        | Length of weaving section | 1,320 | 1,970 | 1,056 |  Discussion:
  How will these weaving sections perform, given these 
    inputs? And, what parameters do we use to characterize the performance of 
    the weaving sections? Take a few minutes to consider these questions. When 
    you are ready, continue to the next page. 
     [ 
    
    Back ] [ 
    
    Continue 
    ] with Sub-Problem 2b  |  
    
    Page Break
  
    | Sub-problem 
    2b: What are the Levels of Service 
    in the Weaving Sections Located in the I-87/Alternate Route 7 Interchange? Step 2. Results The weaving analysis methodology of the HCM produces five distinct results: 
      
      The estimate of space mean 
      speed of weaving and non-weaving traffic in the weaving section.
      Determination of whether the 
      flows are constrained or unconstrained by the weaving section geometry.
      Forecasts of average density 
      based on the predicted speeds.
      Forecasts of level of service 
      based on average density.Estimates of the capacity of the weaving section. The results of the weaving analysis are 
provided in Exhibit 4-28. 
After you've taken the time to review the data in Exhibit 4-28, 
consider the following questions: 
      |  | How does the length of each weaving section affect its 
      operation? |  |  | The volume ratio, VR, is more than twice as high in 
      Weaves B and C as in Weave A; is this significant and if so, why? |  |  | What is the significance of the predicted speeds for 
      the weaving and non-weaving traffic? The weaving speeds are 
      approximately 16 to 18 mi/hr less than the non-weaving speeds for five of 
      the time periods presented in the table; is this important and if so, why? |  |  | Why is the weaving traffic constrained? What is 
      the practical implication of this finding? |  |  | What happens when the weaving flow rate exceeds the 
      model limit? |  |  | In Weaves A and B, the volume ratio, VR, exceeds the model limit; what is 
      the likely result that you would observe in the field? |  Discussion:
  Take a few minutes to consider these questions, and 
your 
answers to them. Proceed to the next page when you are ready. 
    [ 
    
    Back 
    ] [ 
    
    Continue 
    ] with Sub-Problem 2b |  
    
    Page Break
  
  
    
      |  |  
      | 
        
        
          
        | Exhibit 4-28. 
        I-87/Alternate Route 7 interchange Weaving 
        Analyses |  
        | Parameter | Weave A | Weave  
        B | Weave C |  
        | AM Peak | PM Peak | AM Peak | PM Peak | AM Peak | PM Peak |  
        | Dataset 11 | Dataset 12 | Dataset 13 | Dataset 14 | Dataset 15 | Dataset 16 |  
        | Weaving section length (feet) | 1,320 | 1,970 | 1,056 |  
        | Volume ratio,VR | .30 | .31 | .70 | .68 | .76 | .70 |  
        | Weaving ratio, R | .35 | .21 | .36 | .29 | .32 | .44 |  
        | Speeds in weaving section (mph) 
          |  | weaving |  |  | non-weaving |  | 40.2
 56.7
 | 37.5
 55.6
 | 36.9
 53.3
 | 28.0
 44.1
 | 21.1
 31.8
 | 25.0
 41.2
 |  
        | Lanes required for unconstrained flow | 1.5 | 1.5 | 3.3 | 3.6 | 2.3 | 2.0 |  
        | Constrained or unconstrained flow? | Constrained | Constrained | Constrained | Constrained | Constrained | Constrained |  
        | Weaving segment data 
          |  | speed (mph) |  |  | density (pcpmpl) |  |  | level of service |  | 50.5
 9.4
 A
 | 48.9
 12.5
 B
 | 40.6
 12.0
 B
 | 31.7
 38.2
 E
 | 22.9
 76.2
 F
 | 28.4
 35.4
 E
 |  
        | Capacity (pc/hr) | 6,637 | 6,635 | 9,640 | 9,640 | 4,214 | 4,214 |  
            | Model limitations |  
        | A: Does the weaving flow rate exceed the model 
              limit (the maximum allowable weaving flow rate)? | No | No | No | Yes | Yes | No |  
        | B: Does the total flow rate in the section exceed the basic freeway 
        capacity? | No | No | No | No | No | No |  
        | C: Does the volume ratio, VR, exceed the model 
              limit? | No | No | Yes | Yes | Yes | Yes |  
        | D: Type C constraint; not applicable here. | - | - | - | - | - | - |  
        | E: Is the weaving segment longer than 2,500 
              feet? | No | No | No | No | No | No |    |      
    
    Page Break
  
    | Sub-problem 
    2b: What are the Levels of Service 
    in the Weaving Sections Located in the I-87/Alternate Route 7 Interchange? Let's now consider each of the questions posed on the previous 
page, referring again to
Exhibit 4-28.  How does the length of each weaving section affect its 
operation? Let's compare the results for Weaves A and B. In general, providing additional 
length in a weaving section allows drivers more time to complete their maneuvers 
(the intensity of lane changing decreases), often resulting in higher speeds in 
the weaving section. Thus, all other factors being equal, the degree of 
turbulence in Weave B should be lower than Weave A. However, since the 
volumes in Weave B are much higher than in Weave A, the overall weaving 
intensity is higher in Weave B, even with its greater length. The volume ratio, VR, is more than twice as high in Weaves 
B and C as in Weave A; is this significant and if so, why? The volume ratio is 
the ratio of the weaving flow rate to the total flow rate in the weaving 
section. As the proportion of weaving traffic increases, the degree of 
turbulence also increases. Two key results follow from this increased 
turbulence: speeds decrease and density increases. The volume ratio for 
Weaves B and C (ranging from 0.68 to 0.76) shows than between 
two-thirds and three-quarters of the total traffic is required to change lanes. 
This higher degree of turbulence in the traffic stream lowers vehicle speeds in 
the section, and you can see this result directly in the table shown on the 
previous page. What is the significance of the predicted speeds for the 
weaving and non-weaving traffic? The weaving speeds are approximately 16 to 18 
mi/hr less than the non-weaving speeds for five of the time periods presented in 
the table; is this important and if so, why? Safer 
traffic flow always results if all vehicles in the traffic stream are traveling 
at the same speeds. While speed differentials are expected in a weaving 
section, the differences that we observe here are quite high, between 16 and 18 
mi/hr. One of the factors that mitigates this speed differential in weaving 
sections is the degree of separation of the weaving traffic from the non-weaving 
traffic. Because of the nature of a Type A weave, all of the lane changing 
activity occurs in the two lanes adjacent to the crown line, with little or no 
spillover effects in the outer lanes. 
     [ 
    
    Back 
    ] [ 
    
    Continue 
    ] with Sub-Problem 2b |    
    Page Break
  
    | Sub-problem 
    2b: What are the Levels of Service 
    in the Weaving Sections Located in the I-87/Alternate Route 7 Interchange? Why is the weaving traffic constrained? What is the 
practical implication of this finding? 
(see
Exhibit 4-28). The determination of whether a particular 
    weaving segment is operating in an unconstrained or constrained state is 
    based on the comparison of two variables: the number of lanes that must be 
    used by weaving vehicles to achieve equilibrium or unconstrained operation (Nw) 
    and the maximum number of lanes that can be used by weaving vehicles for a 
    given configuration (Nwmax). As we have discussed 
previously, most, if not all, of the lane changing activity associated with 
weaving occurs in the two lanes adjacent to the crown line. In fact, for a 
Type A weave, the number of lanes that can be used by weaving vehicles is 1.4. It is less than 2 since some of the non-weaving vehicles also use these two 
lanes. Our results show that Weave A requires 1.5 lanes (fairly close to 
the number required for unconstrained flow), while Weave B requires from 3.3 to 
3.6 lanes. Clearly, the volumes and proportion of weaving flow associated with 
Weave B requires much more space than is present in this type of weave, so the 
weaving traffic is definitely constrained. What happens when the weaving flow rate exceeds the model 
limit? When weaving flow rates exceed the model limits (in this case, 
2,800 pc/hr for a Type A weave), it is likely that the weaving section will fail, 
regardless of the results from the other parts of the weaving section 
methodologies. For Weave B, during the PM Peak, the weaving volume 
is 4,105 pc/hr, a rate significantly higher than than 2,800 limit cited above. Again, the practical result is a likely breakdown of flow in this segment during 
this time period. In Weaves B and C, the volume ratio, VR, exceeds the model 
limit; what is the likely result that you would observe in the field? For weaving 
sections with five lanes, as in Weave A in this sub-problem, the volume ratio 
limit is 0.35. Both the AM and PM peak results are less than 0.35 for 
Weave A. However, for Weave B, the limit of 0.20 is exceeded in both the 
AM and PM peak periods. In fact, the values of 0.70 and 0.68 are 
significantly higher than the limit with a likely result of poor operations and 
local areas of queuing. The questions that we discussed above are important in helping 
us to understand how the three weaving sections will operate under the given 
conditions. As you consider all of the data together, how would you 
summarize the operations of the three weaving sections? After you have 
considered this question, proceed to the next page for a further discussion of 
this issue.  [ 
    
    Back 
    ] [ 
    Continue 
    ] with Sub-problem 2b |  
    
    Page Break
  
    | Sub-problem 
    2b: What are the Levels of Service 
    in the Weaving Sections Located in the I-87/Alternate Route 7 Interchange? After a review of
Exhibit 4-28 and the discussion 
from the previous page, we can summarize the operations of the three weaving 
sections as follows. Weave A is forecasted to operate at levels of service A and B 
during the AM and PM peak periods, respectively. While there is a high 
speed differential between the weaving and non-weaving vehicles, the proportion 
of weaving traffic (volume ratio) is low (0.31 and 0.30, respectively) during 
the two time periods. This means that the overall speed of all vehicles in 
the section is over 50 mi/hr and the resultant densities (9.4 pc/mi/lane and 
12.5 pc/mi/lane) are low. We can conclude that, based on today's volumes, 
Weave A will operate at a very acceptable level for motorists traveling through 
this section. There is no reason to consider any changes to the design of 
this weaving section. We should further note that all model limitations are met by 
the conditions for Weave A, so we can be reasonably confidant of our 
conclusions. Weave B, by contrast, is forecasted to operate at level of 
service B during the AM peak but only level of service E during the PM peak 
period. What are the factors that cause this poor operation during the afternoon 
period?  
     [ 
    
    Back 
    ] [ 
    
    Continue ] with Sub-Problem 
    2b |  
    
    Page Break
  
    | Sub-problem 
    2b: What are the Levels of Service 
    in the Weaving Sections Located in the I-87/Alternate Route 7 Interchange? By referring once again to the summary of results presented in
Exhibit 4-28 we see much higher flow rates in the PM 
peak than in the AM peak, 5,447 veh/hr in the PM and only 2,196 veh/hr in the AM. And, while there is a very high volume ratio (VR) during both periods, the lower 
total volumes mitigate this condition in the AM peak. However, in the PM 
peak, the high volume ratio combined with the high overall flow rates result in 
an overall speed of 31.7 mi/hr in the weaving section and a density of 38.2 
pc/mi/lane.  Furthermore, both the volume ratio and the total weaving 
volume model limits are exceeded during the PM peak. The likely result is 
a breakdown of operations and queuing at some locations in the section. We 
should note that the volume ratio limit is also exceeded in the AM peak, again 
resulting in poor operations.  We can conclude that, even though the forecasted level of 
service is B for the AM peak, both time periods will experience poor operations 
with breakdowns in flow to be expected. While we won't consider this 
sub-problem in more detail here, it would be valuable for you to review the 
results presented here and identify geometric improvements that you think might 
improve the operational performance of this weaving section.  The operation of Weave C is even worse, with forecasts of 
level of service F for the AM peak and level of service E for the PM peak. With the high density and the 
failing conditions present for this 
analysis, we might ask whether or not we should consider another tool in 
addition to the HCM, such as a microscopic simulation model, to evaluate this weaving section. We will discuss this 
issue in more detail in Problem 5 of Case Study 4. [ 
    
    Back 
    ] [ 
    
    Continue 
    ] with Sub-Problem 2c |  
    
    Page Break
  
    | Sub-problem 2c: What 
is the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? Step 1. Setup 
        In this problem, we will consider the merge point between 
        I-87 northbound and the ramp from westbound Alternate Route 7. The ramp 
        itself is complex since it also has a merge point with the intersection 
        of the on-ramp from U.S. 9. You can learn more about the ramp by 
        clicking on the Exhibit caption. 
    As we begin this sub-problem, let's consider several issues that relate to 
    the analysis of a freeway ramp junction: 
      |  | Should we consider only the vicinity of the junction 
      itself, or are there other areas that we should consider as well? |  |  | What input data are needed to conduct this 
      analysis? |  |  | What is the primary measure of effectiveness for a merge 
      point analysis? |  |  | What parameters are forecasted by the merge point 
      analysis models in the HCM? |  |  | What are some of the limitations of the merge point 
      analysis model that we must keep in mind when applying it to this 
      sub-problem? |  Discussion:
  Take a few minutes to consider 
    these questions. When you are ready, continue to the next page. 
     [
    
    
    Back 
    ] [ 
    
    Continue 
    
    ] with Sub-problem 2c  |  
    
    Page Break
  
  
    
      |  |  
      | Merge point This merge point is formed by the 
intersection I-87 northbound mainline and the ramp from Alternate Route 7 westbound. 
       |      
    
    Page Break
  
    | 
Sub-problem 2c: What 
is the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? 
Let's now consider each of these questions: Should we consider only the vicinity of the junction 
    itself, or are there other areas that we should consider as well? 
    The ramp junction methodology focuses on what is called the merge influence 
    area. The merge influence area is defined as the area from the merge 
    point to 1,500 feet downstream for lanes 1 and 2 of the freeway mainline. It is within this area that most of the effect of the merging traffic into 
    the freeway mainline is observed. For this problem, this area is on I-87 
    from the 
    point of the ramp merge to 1,500 feet downstream. But we should also 
    consider other parts of the ramp itself. For example, the merge with 
    the U.S. 9 ramp creates some turbulence in the traffic stream as the two 
    ramps come together and drop from two lanes to one in a very short 
    distance. Additionally, we must consider the 
    capacity of the ramps themselves. We'll discuss each of these points 
    later in the sub-problem. One other point must be 
    made. When we are considering a merge analysis, we need to look at the 
    location of adjacent on-ramps and off-ramps. If these ramps are within 
    1,500 feet,  the effect that they have on the lane distribution of traffic 
    must also be considered. Since there are no ramps within 1,500 feet of 
    this merge area, this issue is not relevant to this problem. 
    [ 
    
    Back 
    ] [ 
     
    
    
    Continue] with Sub-Problem 2c |  
    
    Page Break
  
    | 
Sub-problem 2c: What 
is the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? 
    What input data is needed to conduct this 
    analysis? To conduct an operational analysis of a merge 
    area, we need to have the following input data: 
      |  | number of lanes on the freeway |  |  | free flow speed on the freeway |  |  | freeway volume just upstream of the merge point |  |  | free flow speed of the ramp |  |  | ramp volume |  |  | number of lanes on the ramp |  |  | length of the acceleration lane(s) |  What the primary measure of effectiveness for a merge 
    point analysis? We are conducting an operational analysis, so we 
    want to be able to forecast the level of service of the merge influence 
    area. The HCM uses 
    density as the primary measure of effectiveness 
    from which to determine the level of service. Density is expressed in 
    terms of vehicles per mile per lane. What 
      parameters are forecasted by the merge point analysis models in the HCM?
      To forecast the density of traffic in the merge influence 
      area, the HCM uses several steps (and models). First, the flow rate 
      in the merge influence area is computed. Recall that this is the flow rate 
      in lanes 1 and 2 in the area 
      just downstream of the merge. Next, the density in the merge area is 
      computed and the level of service is determined. Finally, the speed 
      is computed. What are some of the limitations 
    of the merge point analysis model that we must keep in mind when applying it 
    to this sub-problem? One of the major limitations of 
      the ramp junction procedure in the HCM is that it does not apply when demand exceeds capacity. If demand exceeds capacity, we 
    need to consider another procedure, possibly microscopic simulation. 
    [ Back ] [ 
    Continue ] with Sub-problem 2c 
     |  
    
    Page Break
  
    | Sub-problem 2c: What 
is the level of service at the ramp junction at the northbound on-ramp to 
I-87? Step 2. Results The input data for this problem is gathered from several 
    sources. We can use the aerial photographs in
    Exhibit 4-17 and the map in
    Exhibit 4-18 that were 
    presented earlier in this problem to determine the number of lanes on the I-87 mainline and 
    on the ramp itself. The length of the acceleration lane was also 
    determined from the map and aerial photos. We determined the free flow 
    speeds on the freeway and on the ramp using data collected previously by the 
    New York State DOT. The volume data is a topic that is worthy of additional 
    discussion. While we could use ground counts collected by the DOT, we 
    must be careful. Why? These counts represent service volumes, or 
    the actual volumes using the facility during a given time interval. However,  to have a true estimate of the facility performance, we 
    must instead consider demand volume, or the number of users of a given segment during a specific period of time. Particularly when 
    congestion exists, it is often difficult to estimate demand volume. Remember 
    that the distinction between demand and volume is this: demand is the number 
    of system users desiring service over the course of a given time 
    interval, whereas volume is the number of system users actually served 
    during that same time interval. With this distinction in mind, you can see 
    that demand and volume are equivalent to one another only when the system is 
    operating in an undersaturated mode. The data used for this problem are summarized in Exhibit 
    4-30. 
      
      
      
        | Exhibit 4-30. Northbound Ramp Input 
        Data |  
        | Freeway data | AM Peak | PM Peak |  
        | Number of lanes, N | 3 |  
        | Free flow speed, SFF (mph) | 55 |  
        | Volume (pc/hr) | 1,000 | 4,800 |  
        | Ramp data | AM Peak | PM Peak |  
        | Ramp volume (pc/hr) | 765 | 1,900 |  
        | Number of lanes on-ramp, N | 1 |  
        | Free flow ramp speed, SFR 
        (mph) | 35 |  
        | Length of acceleration lane, LA | 500 |  Continue to the next page to see the results of applying 
    the HCM ramp junction analysis to the conditions found in these two time 
    periods. 
    [ 
    Back ] [ 
    
    Continue ] with Sub-Problem 2c  |  
    
    Page Break
  
    | Sub-problem 2c: What 
is the level of service at the ramp junction at the northbound on-ramp to 
I-87? The data produced from the HCM analysis of the merge point 
    located at northbound I-87 and the on-ramp from Alternate Route 7 westbound are 
    shown in Exhibit 4-31.  
      
      
      
        | Exhibit 4-31. Results of HCM 
        Analysis on Merge |  
        | Output data | AM Peak | PM Peak |  
        | Dataset 17 | Dataset 18 |  
        | PFM | 0.59 | 0.59 |  
        | V12, pc/h | 656 | 3,154 |  
        | VFO actual, pc/h | 1,957 | 7,444 |  
        | VFO maximum, pc/h | 6,750 | 6,750 |  
        | VR12 actual, pc/h | 1,504 | 5,265 |  
        | VR12 maximum, pc/h | 4,600 | 4,600 |  
        | Density, pc/mi/lane | 13.7 | 42.4 |  
        | LOS for ramp-freeway junction area of 
        influence | B | F |  
        | Speed-ramp influence area, mph | 51.2 | 41.6 |  
        | Speed-outer lanes, mph | 55.0 | 49.0 |  
        | Speed-all vehicles, mph | 52.0 | 43.5 |  Carefully study the information 
    presented in the table. Using this information, consider the following 
    questions: 
      |  | What is the significance of the parameter, PFM? |  |  | Which data from the table above describe the nature of 
      the flow of traffic in the merge influence 
      area? |  |  | What is the basis for the forecast of level of service? |  |  | How would you describe the operation of the merge point 
      in the PM peak period? |  Discussion:
  Take a few minutes to consider 
    these questions. When you are ready, continue to the next page. 
    [ Back ] [
    Continue ] with Sub-Problem 2c  |  
    
    Page Break
  
    | Sub-problem 2c: What 
is the level of service at the ramp junction at the northbound on-ramp to 
I-87? Let's now consider the questions from the previous page 
    and Exhibit 4-31. What is the significance of the parameter, PFM?
    One of the most important functions of the merge point analysis is to 
    estimate the lane distribution of traffic in the vicinity of the merge 
    point. The proportion of the approaching freeway flow remaining in 
    lanes 1 and 2 immediately upstream of the merge point is noted as PFM. This parameter depends on both the number of lanes on the freeway mainline 
    and the length of the acceleration lane from the ramp to the mainline. 
    For this particular analysis, the value of PFM 
    is 0.59. This means that 59 percent of the approaching freeway flow 
    remains in lanes 1 and 2 immediately upstream of the merge point. If 
    the freeway had more lanes at this point, this value would be lower, as more 
    of the mainline traffic would avoid the turbulence of the merge area. 
    Which data from Exhibit 4-31 
    describe the nature of the flow of traffic in the merge influence area? Several model outputs 
    help us to understand the nature of the flow in the merge area. The 
    flow rate in the merge influence area (vR12) is compared to the 
    capacity of the area to determine whether this area is under capacity or 
    over capacity. The density and speed of the merge area is also computed; the 
    density is used to determine level of service. 
    [ 
    
    Back 
    ] [ 
    
    
    Continue 
    ] with Sub-problem 
    2c  |  
    
    Page Break
  
    | Sub-problem 2c: What 
is the level of service at the ramp junction at the northbound on-ramp to 
I-87? Note that the during the PM peak, vR12 is 5,265 
    passengers cars per hour, 
    a flow rate which exceeds the capacity of the merge influence area (4,600 
    pc/h). The implication is important: a significant part of the demand (5,264 - 4,600 = 664) 
    can't be served during the analysis period. This unserved demand is diverted to 
    the next analysis period. The density during the PM peak is 42.4 pc/mi/lane, 
    while the speed is forecasted to be just below 42 mi/hr.
    
     What is the basis for the forecast of level of service?
    The basis for forecasting level of service is the density of traffic 
    flow. For this case, the density during the PM peak is 42.4 
    pc/mi/lane, which is level of service F. The level of service during 
    the AM peak is B, based on a density estimate of 13.7 pc/mi/ln. 
    How would you describe the operation of the merge point in 
    the PM peak period? The operation of the merge point during the PM 
    peak period is poor. The demand exceeds the capacity, the density is high, 
    and the speed is relatively low. 
    Since the demand exceeds capacity, 
    we need to consider another analysis tool, such as a microscopic simulation 
    tool, that will enable us to have a more accurate characterization of the 
    operational performance of this ramp junction during the PM peak period. Remember that the HCM states in chapter 25 
    that this methodology does not take into account oversaturated conditions. The use of micro-simulation will be illustrated in problem 5 of this case 
    study. 
    [ 
    
    Back 
    ] [ 
    
    
    Continue 
    ] with Sub-Problem 2d |  
    
    Page Break
  
    | Sub-problem 2d: How 
Can We Improve the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? Step 1. Setup 
        The merge point that we considered in sub-problem 2c was 
        over capacity during the PM peak hour. Queues extended over much of 
        the length of the ramp. The demand exceeded capacity and the HCM 
        methodology couldn't be used for this analysis under conditions 
        present during the PM peak hour. But while the HCM methodology 
        couldn't forecast the performance, we do know that the facility will 
        fail since the demand was found to exceed capacity. 
    Consider how we could mitigate this problem. What possible 
    changes in the design of the ramp merge area should be considered? To 
    provide insight into possible geometric mitigations, we can look more 
    closely at the forecast models. There are five variables of prime 
    importance: 
          
          Free flow speed on the ramp.
          Free flow speed on the mainline.
          Number of lanes on the ramp.
          Number of lanes on the mainline.
          Length of the acceleration lane in the merge area. Many factors determine whether or not changing any 
          of these variables is feasible. But we can use the HCM procedure 
          to determine how much change we can expect in the operational 
          performance if one or more of these variables is modified. Discussion:
  What possible design changes would you suggest to mitigate 
    this problem? When you are ready, continue to the next page. 
    [ 
    
    
    Back ] [ 
    
    Continue 
    ] with Sub-Problem 2d  |  
    
    Page Break
  
    | Sub-problem 2d: How 
Can We Improve the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? Step 1. Setup 
        The merge point that we considered in sub-problem 2c was 
        over capacity during the PM peak hour. Queues extended over much of 
        the length of the ramp. The demand exceeded capacity and the HCM 
        methodology couldn't be used for this analysis under conditions 
        present during the PM peak hour. But while the HCM methodology 
        couldn't forecast the performance, we do know that the facility will 
        fail since the demand was found to exceed capacity. 
    Consider how we could mitigate this problem. What possible 
    changes in the design of the ramp merge area should be considered? To 
    provide insight into possible geometric mitigations, we can look more 
    closely at the forecast models. There are five variables of prime 
    importance: 
          
          Free flow speed on the ramp.
          Free flow speed on the mainline.
          Number of lanes on the ramp.
          Number of lanes on the mainline.
          Length of the acceleration lane in the merge area. Many factors determine whether or not changing any 
          of these variables is feasible. But we can use the HCM procedure 
          to determine how much change we can expect in the operational 
          performance if one or more of these variables is modified. Discussion:
  What possible design changes would you suggest to mitigate 
    this problem? When you are ready, continue to the next page. 
    [ 
    
    
    Back ] [ 
    
    Continue 
    ] with Sub-Problem 2d  |  
    
    Page Break
  
    | Sub-problem 2d: How 
    Can We Improve the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? We will explore three possible mitigation options in this 
    sub-problem: adding a lane to the freeway mainline; adding a lane to the 
    ramp; and lengthening the acceleration lane. Each of these mitigations 
        requires minor changes in the input data. If we add a lane to the 
        freeway mainline, one parameter change is required: the number of lanes 
        on the freeway mainline. If we add a lane to the ramp, again, one 
        parameter change is required: the number of lanes on the ramp. Similarly, if we change the length of the acceleration lane, this parameter 
        must be modified. In 
    the next several pages, we will consider the results of these parameter 
    changes. You can follow the solutions and relevant discussion for each of 
    these three changes through the links below: 
    Adding a lane to the freeway 
    mainline 
    Adding a lane to the ramp 
    Lengthening the acceleration 
    lane 
     [ 
    
    Back 
    ] [ 
    
    Continue ] with Sub-Problem 2d  |  
    
    Page Break
  
    | Sub-problem 2d: How 
    Can We Improve the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? Step 2. Results Exhibits 4-32 and 4-33 show the impact of adding a lane to the 
    freeway mainline. Exhibit 4-32 shows the input data while Exhibit 4-33 shows the output data produced from the HCM analysis. 
      
      
      
        | Exhibit 4-32. Additional Lane  on Freeway Mainline Input Data
 |  
        | Freeway data | AM Peak | PM Peak |  
        | Dataset 19 | Dataset 20 |  
        | Number of lanes, N | 4 |  
        | Free flow speed, SFF | 55 |  
        | Volume | 1,000 | 4,800 |  
        | Ramp data | AM Peak | PM Peak |  
        | Ramp volume | 765 | 1,900 |  
        | Number of lanes on-ramp, N | 1 |  
        | Length of acceleration lane, LA | 500 |    
      
      
      
        | Exhibit 4-33. Additional Lane  on Freeway Mainline Output Data
 |  
        | Output data | AM Peak | PM Peak |  
        | PFM | 0.24 | 0.08 |  
        | V12, pc/h | 261 | 415 |  
        | VFO actual | 1,957 | 7,444 |  
        | VFO maximum | 9,000 | 9,000 |  
        | VR12 actual | 1,109 | 2,526 |  
        | VR12 maximum | 4,600 | 4,600 |  
        | Density, pc/mi/lane | 10.6 | 21.1 |  
        | LOS for ramp-freeway junction area of 
        influence | B | C |  
        | Speed-ramp influence area, mph | 51.3 | 50.8 |  
        | Speed-outer lanes, mph | 55.0 | 47.5 |  
        | Speed-all vehicles, mph | 52.8 | 48.6 |  After reviewing the output data shown in 
    Exhibit 4-33, 
    consider the following questions: 
      Discussion:|  | What is the most significant change in the performance 
      of the merge area as a result of the addition of the lane to the freeway 
      mainline? |  |  | Does the addition of the lane produce acceptable 
      performance of the merge area? |  
  Take a few minutes to consider 
    these questions. When you are ready, continue to the next page. 
    [ 
    
    Back 
    ] [ 
     
    
    Continue 
    ] with Sub-Problem 2d  |  
    
    Page Break
  
    | Sub-problem 2d: How 
    Can We Improve the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? Exhibit 4-34 shows the results of adding a lane to the 
    freeway mainline, with a direct comparison to the conditions before the lane 
    was added. The most direct result of adding a lane is the increase in 
    the mainline capacity from 6,750 to 9,000 pc/h. This has several related 
    impacts. The proportion of approaching freeway flow remaining in lanes 
    1 and 2, PFM, decreases from 0.59 to 0.08, because the traffic 
    remaining on the mainline is more likely to avoid the congestion 
    inherent in the merge area: two lanes are now available for through traffic 
    rather than one in the  before case. This also shows in the traffic in the
    merge influence area 
    (lanes 1 and 2 plus on-ramp), VR12, 
    decreases from 5,265 to 2,526. After the lane is added, this flow rate 
    is below the maximum (capacity) of 4,600. The overall performance of the merge area increases 
    dramatically from LOS F before to LOS C after the addition of the lane. The speed of vehicles in the ramp influence area increases from 41.6 to 50.8 
    mph. This change has a clear and dramatic effect in the performance of 
    the freeway. 
      
      
      
        | Exhibit 4-34. Existing and 
        Additional Mainline Lane Configurations Compared  |  
        | Output data | PM Peak 
        (Before) | PM Peak 
        (After) |  
        | PFM | 0.59 | 0.08 |  
        | V12, pc/h | 3,154 | 415 |  
        | VFO actual | 7,444 | 7,444 |  
        | VFO maximum | 6,750 | 9,000 |  
        | VR12 actual | 5,265 | 2,526 |  
        | VR12 maximum | 4,600 | 4,600 |  
        | Density, pc/mi/lane | 42.5 | 21.1 |  
        | LOS for ramp-freeway junction area of 
        influence | F | C |  
        | Speed-ramp influence area, mph | 41.6 | 50.8 |  
        | Speed-outer lanes, mph | 49.0 | 47.5 |  
        | Speed-all vehicles, mph | 43.5 | 48.6 |  
    [ 
    
    Back 
    ] [ 
     
    Continue 
    ] with Sub-Problem 2d  |  
    Page Break
  
    | Sub-problem 2d: How 
    Can We Improve the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? Exhibits 4-35 and 4-36 show the 
    effect of adding a lane to the ramp so that two lanes are maintained on the 
    ramp for its entire length from Alternate Route 7 to I-87 North. 
      
      
      
        | Exhibit 4-35. Additional Ramp Lane 
        Input Data |  
        | Freeway data | PM Peak 
        (Before) | PM Peak 
        (After) |  
        | Dataset 21 | Dataset 22 |  
        | Number of lanes, N | 3 | 3 |  
        | Free flow speed, SFF | 55 | 55 |  
        | Volume | 4,800 | 4,800 |  
        | Ramp data | PM Peak 
        (Before) | PM Peak 
        (After) |  
        | Ramp volume | 1,900 | 1,900 |  
        | Number of lanes on-ramp, N | 1 | 2 |  
        | Length of acceleration lane, LA | 500 | 500 |  
        |  |  
        | Exhibit 4-36. Additional Ramp Lane Output Data |  
        |  | PM Peak 
        (Before) | PM Peak 
        (After) |  
        | Output data | Dataset 21 | Dataset 22 |  
        | PFM | 0.59 | 0.56 |  
        | V12, pc/h | 3,154 | 2,960 |  
        | VFO actual | 7,444 | 7,444 |  
        | VFO maximum | 6,750 | 6,750 |  
        | VR12 actual | 5,265 | 5,071 |  
        | VR12 maximum | 4,600 | 4,600 |  
        | Density, pc/mi/lane | 42.5 | 34.7 |  
        | LOS for ramp-freeway junction area of 
        influence | F | F |  
        | Speed-ramp influence area, mph | 41.6 | 44.5 |  
        | Speed-outer lanes, mph | 49.0 | 48.0 |  
        | Speed-all vehicles, mph | 43.5 | 45.6 |  After reviewing the output data 
    shown in Exhibit 4-36, consider the following questions: 
      |  | What is the most significant change in the performance 
      of the merge area as a result of the addition of the lane to the freeway 
      mainline? |  |  | Does the addition of the lane produce acceptable 
      performance of the merge area? |  Discussion:
  Take a few minutes to consider 
    these questions. When you are ready, continue to the next page. 
    [ 
    
    Back 
    ] [ 
    
    Continue ] with Sub-Problem 2d  |  
    
    Page Break
  
    | Sub-problem 2d: How 
    Can We Improve the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? A review of 
    Exhibit 4-36 shows some 
    minor improvements in the operational performance of the merge area. The density is reduced from 42.5 to 34.7 and the speed of the ramp influence 
    area increases from 41.6 to 44.5 mph. But should we believe these 
    forecasts? No. Since the forecasted volume in the 
    merge area (5,070) 
    exceeds the capacity (4,600) 
    of the area, we know that the model cannot be applied realistically to these 
    conditions. Thus, while we can produce output results, we need to know 
    that in this case, the results cannot be used with any degree of certainty 
    to help us with this analysis. Again, if we desired to have a more 
    definitive assessment of the performance of this alternative, we would have 
    to use another analysis tool, 
    perhaps a microscopic simulation tool. Continue on to the next page to view the 
    effect of 
    extending the length of the acceleration lane on the performance of the 
    merge area. 
    [ 
    
    Back ] 
    [ 
     
    
    Continue 
    ] with Sub-Problem 2d  |  
    
    Page Break
  
    | Sub-problem 2d: How 
    Can We Improve the Level of Service at the Ramp Junction at the Northbound On-Ramp to 
I-87? Exhibit 4-37 shows the effect of increasing the 
    acceleration lane from 500 (existing condition) to either 
    1,000 
    feet or 1,500 feet. Again, as with the addition of a lane to the ramp, the effect is not 
    significant. In fact, as we saw before, the demand still exceeds the 
    capacity of the merge influence area and so, here again, we cannot depend on the results 
    from the HCM model for this analysis.     
      
      
      
        | Exhibit 4-37. Effect of Lengthening 
        the Existing Acceleration Lane |  
        | AM Peak Hour (7 am - 8 am) |  
        | Dataset | Acceleration lane (feet) | Density | LOS | Speed |  
        | Dataset 23 | 500 | 13.7 | B | 51 |  
        | Dataset 24 | 1,000 | 10.7 | B | 52 |  
        | Dataset 25 | 1,500 | 7.7 | A | 52 |  
        | PM Peak Hour 
        (4 pm - 5 pm) |  
        | Dataset | Acceleration lane (feet) | Density | LOS | Speed |  
        | Dataset 26 | 500 | 42.4 | F | 42 |  
        | Dataset 27 | 1,000 | 39.9 | F | 41 |  
        | Dataset 28 | 1,500 | 37.3 | F | 41 |  
    [ 
    
    Back 
    ] [ 
    
    Continue 
    ] with Problem 2 Analysis  |  
    
    Page Break
  
    | Problem 2: Analysis We have produced a 
significant amount of information about the operation of the I-87/Alternate Route 7 interchange using the HCM. Let's summarize the key points from the four sub-problems we've just 
completed. In sub-problem 2a, we divided the interchange into manageable 
components that could be analyzed using the procedures of the HCM, including 
both weaving sections and ramp junctions. In sub-problems 2b, 2c, and 2d, 
we analyzed the operation of the three weaving sections and one of the four ramp 
junctions. Exhibit 4-38 summarizes the results of these analyses. 
      
      
      
        | Exhibit 4-38. LOS and HCM Methodology Applicability Under Conditions Investigated
 |  
        | Location | AM peak 
        hour | PM peak 
        hour |  
        | LOS | Model conditions 
        satisfied? | LOS | Model conditions 
        satisfied? |  
        | Weave A | A | 
        Yes | B | 
        Yes |  
        | Weave B | B | No | E | No |  
        | Weave C | F | No | E | No |  
        | I87/SR7 merge |  |  
        | Existing | B | Yes 
   | F | No |  
        | Add lane to freeway | _ | C | Yes |  
        | Add lane to ramp | _ | F | No |  
        | Lengthen acc 
        lane | _ | F | No |  Weave A, the 
    section of eastbound Alternate Route 7 from the 
    I-87 on-ramp to the US 9 off-ramp, operates at an acceptable level of 
    service A during the AM peak hour and B during the PM peak hour. In 
    both cases, we can have confidence in the model forecasts, since the model's 
    boundary conditions are satisfied. At both Weaves B and C, however, poor levels of service 
    are forecasted, and the model conditions are not satisfied. We can 
    assume that field conditions are poor with periodic queuing and delays for 
    motorists traveling through these weaving sections. We also 
    forecasted levels of service for the northbound I-87/Alternate Route 7 merge point. During the AM peak, the level of 
    service is expected to be B, certainly an acceptable level of performance. However, for the PM peak hour, the level of service is forecasted to be F. Further, the demand exceeds the capacity, implying that the HCM model should 
    not be applied for these conditions. 
    [ 
    
    Back 
    ] [ 
    
    Continue 
    ] to Discussion of Problem 2  |  
    
    Page Break
  
    | Problem 2: Discussion There are several issues that we should consider as part of 
the analysis  we have just completed. First, while we have 
completed an analysis of the major components of the I-87/Alternate Route 7 interchange, we don't have results that we 
can say are completely reliable. For two of the weaving sections and for 
the ramp junction, the model boundaries were exceeded, thus putting some 
uncertainty on the results produced by the HCM analysis. Second, while we have 
looked at the components of the interchange, we are still conducting this 
analysis in some isolation. How does the operation of the interchange affect the 
mainline section of I-87, particularly in the vicinity of the various ramp 
junctions? How does the interchange affect the operation of Alternate Route 7? These questions and 
issues dictate the need to consider two 
additional problems in this case study. In Problem 4, we will use the 
Freeway Systems methodology from Chapter 22 of the HCM to consider Alternate Route 7 
as a system, from the I-87 interchange to the I-787 interchange. This 
system perspective, looking at how the individual components operate together, 
is important for several reasons. One of these is that drivers consider this perspective 
every time they use (or judge) the facility. Drivers do not generally think 
about the performance characteristics of individual pieces of the freeway 
system, and then use this to judge the overall quality of their driving 
experience. Rather, their perception of the quality of service they have 
received develops over time, and they would typically describe the freeway they 
drove on as a single entity as opposed to a sequence of individual elements. In Problem 5, we will 
use a micro-simulation model to help us study the performance of the segments of 
Alternate Route 7 that could not be 
adequately analyzed by the HCM, particularly those segments in which demand 
exceeded capacity. 
    [ Back ] to 
    Problem 2 Analysis [
    Continue ] 
    to Problem 3 |  |