Case Study 4: Problem 4 -
Printable
Home
> Problem 4 - Page 1 of 1 Problem 4: Analysis of the
Alternate Route 7 Freeway Facility
Printable Version
In the previous three problems of this case
study, we examined the operation of individual segments of Alternate Route 7,
including basic freeway segments, weaving sections, and ramp junctions. In
this problem, we will step back and consider the segments as drivers actually
see them: part of a complete freeway facility. This perspective is also the way
that the New York State DOT views this facility, a facility operating as a whole
unit rather than separate components.
In addition, there are interactions between
the various segments of this freeway that we have previously studied. For
example, we earlier considered the weaving section that exists on eastbound
Alternate Route 7 between the I-87 NB on-ramp and the U.S. Route 9 off-ramp on the
western portion of the facility. A weaving section is by its nature a
combination of two ramp junctions. Another example of the interaction
between segments is when the flows from one part of the freeway interact with
the flows from another part of the freeway. If a bottleneck exists, say as
a result of a temporary lane closure, the flow from the bottleneck may spill
back a mile or more upstream.
The question that we consider in this
problem is how to determine the performance of the facility as a whole,
then use this analysis to help us to identify (or verify) problems that exist in
the field today.
We will consider three sub-problems to
illustrate the application of the freeway facility analysis procedure.
Sub-problem 4a - How
should the Alternate
Route 7 facility be divided up for an HCM operational analysis?
Sub-problem 4b - What is
the operational performance of Alternate Route 7 during the off peak period?
Sub-problem 4c - What is the operational
performance of Alternate Route 7 during the peak period?
Continue with sub-problem 4a when you are ready.
[ Back ] to
Problem 3 [
Continue ] with
Sub-Problem 4a |
Page Break
Home >
Problem 4 >
Sub-problem 4a - Page 1 of 4 Sub-problem 4a: Potential Left-Turn Capacity
Step 1. Setup
We will now look at the operation of the northbound left-turn movement and consider the potential left-turn capacity of that
movement as it crosses the eastbound movement.
Exhibit 3-26 shows the northbound left-turn queue at the
Okeechobee Road Intersection. Observe the number of heavy vehicles in the
traffic stream.
The heavy northbound congestion evident in the current operation (see
Exhibit 3-26)
suggests that the capacity of the northbound left turn should first be
examined by the basic principles set forth in the HCM before the full
procedure is invoked by software. This step will give us a better
understanding of the basic relationships that apply to TWSC control.
Consider:
Discussion:
Take
a few minutes to consider these questions. Click continue when you are
ready to proceed. [
Back ] to Problem 4 [
Continue ] with
Sub-Problem 4a |
Page Break
Home
> Problem 4 >
Sub-problem 4a - Page 2 of 4 Sub-problem 4a:
Northbound Left-Turn Capacity
Step 2: Results
What volume-related factors affect the northbound left-turn movement
capacity?
The basic relationship
between movement capacity is defined by the conflicting flow rate and the
driver characteristics (critical gap and follow-up time). Using what are
widely considered default values for critical gap and follow up time as
described in HCM Exhibit 17-5, one can graphically represent the
relationship as shown below (which is similar to HCM Exhibit 17-7). This
exhibit shows how the capacity for the stopped movement decreases as the
conflicting volume (flow ratio on the x axis) increases. At very high levels of conflicting traffic,
the capacity for the stopped movement becomes effectively zero because the
availability of acceptable gaps is eliminated.
What geometry-related factors affect the northbound
left-turn movement capacity? How could we take into account the separation of the
roadways? A review of the
aerial
shows that the median space provides a potential refuge for vehicles that
use two-stage gap acceptance. The right-turning traffic is removed from the
intersection. Thus, consideration of the northbound left-turn movement
becomes the eastbound through traffic as the only opposing movement
in consideration of the first part of the two stage movement. The analysis
that follows considers the first stage in consideration of the capacity of
the northbound Krome Avenue left-turn movement. It should be noted that this
is a simplification and may not consider the operation of vehicles in the
median blocking northbound left-turn traffic from initiating this first
stage of the two-stage gap acceptance. In this example, it is clear that the
primary conflict under these traffic conditions is the eastbound through
movement which is significantly higher than the westbound through movement.
[
Back ] [ Continue ] with
Sub-Problem 4a |
Page Break
Home > Problem 4 >
Sub-problem 4a - Page 3 of 4
Sub-problem 4a:
Northbound Left-Turn Capacity
Exhibit 3-27
shows several lines
plotted on this exhibit which represent different types of stopped movements
(through, left, etc.). The dashed red line has been added to identify the
relationship for the minor street northbound left-turn movement. The
westbound left-turn movement (solid black line) represents the potential
capacity for the major street left turn, which must yield to the oncoming
eastbound traffic and has a higher capacity than the movements entering from
the minor street.
 |
Exhibit
3-27. Potential capacity of a stop-controlled movement as a function of
the conflicting traffic volume. (Source: HCM Exhibit
17-7). |
The dotted blue lines near
the bottom of the graph represent the demand volume (Volume) and the
estimated potential capacity (Capacity) based on the conflicting volume for
the northbound left-turn movement.
[
Back ] [ Continue ] with
Sub-Problem 4a |
Page Break
Home > Problem 4 >
Sub-problem 4a - Page 4 of 4
Sub-problem 4a: Northbound Left-Turn Capacity
The logical conclusion to
draw from the graph on the preceding page is that the minor street conflicting movement volume is
too heavy to permit a viable TWSC operation at this intersection. Without
going into the numbers, the graphical presentation indicates that the demand
volume is considerably higher than the capacity. Keeping in mind that the
potential capacity for a movement does not consider the competition from
other movements at the same priority level, it will generally represent an
optimistic assessment of the capacity. When even this optimistic assessment
fails, you would conclude that there is no point in proceeding any further
with the investigation of TWSC.
Normally you would stop at
this point and look at some other control alternatives. We will, however,
carry the TWSC concept into a couple of other sub-problems to illustrate
some features of the HCM analysis procedure and to set the stage for the
consideration of other alternatives.
[
Back ] [ Continue ] to
Sub-Problem 4b |
Page Break
Home >
Problem 4 >
Sub-problem 4b - Page 1 of 4 Sub-problem 4b:
Two-way Stop Controlled
Analysis
Step 1.
Setup
Exhibit 3-28. |

|
The unusual geometrics,
especially the physical distance separating the conflicting movements at
this intersection, will require some thought
about how to represent the intersection for analysis by the HCM procedures.
The conventional intersection conflict points are shown in Exhibit 3-28. Because of the wide separation of conflicts at this intersection,
it should occur to us that we probably shouldn’t treat this situation as a
typical urban intersection.
In this
sub-problem, we will carry out a conventional intersection analysis. Then we
will examine the results to determine if our treatment was appropriate.
Consider:
Discussion:
Take
a few minutes to consider these questions. Click continue when you are
ready to proceed.
[ Back
] to Sub-Problem 4a [
Continue ] with Sub-Problem 4b |
Page Break
Home
> Problem 4 >
Sub-problem 4b - Page 2 of 4 Sub-problem 4b:
Two-way Stop Controlled
Analysis
What movements are considered in the HCM procedures?
The HCM procedures compute
the capacity, control delay, and level of service for all movements that must
yield to other movements, including the left turns from the major street.
Through and right-turn movements on the major street are excluded from the
analysis and are assumed to have no delay.
This simplifying
assumption raises a point of interest. Heavy vehicles making right turns
will sometimes cause significant delays to traffic on the major street. This
phenomenon is overlooked by the HCM procedure. If such delays are of concern
to a particular analysis, it will be necessary to apply microscopic
simulation modeling tools to supplement the HCM analysis. For purposes of
this discussion, we will assume that traffic delay to the through movements
on the major street is not an issue.
Exhibit 3-29. LOS Thresholds for
TWSC Intersections
(HCM Exhibit 17-2) |
LOS |
Average Control Delay
(sec/veh) |
A |
≤ 10 |
B |
> 10–15 |
C |
> 15-25 |
D |
> 25-35 |
E |
> 35-50 |
F |
>50 |
What is the basis for determining LOS in the unsignalized
intersections methodology?
The level of service is
based on the control delay according to Exhibit 3-29. HCM Chapter
17 prescribes the full procedure for computing control delay.
[
Back ] [ Continue ] with Sub-Problem 4b
|
Page Break
Home
> Problem 4 >
Sub-problem 4b - Page 3 of 4 Sub-problem 4b:
Two-way Stop Controlled
Analysis
Step 2. Results
The results of this
analysis are presented in Exhibit 3-30. These results reaffirm the conclusions
drawn from sub-problem 4a, specifically that TWSC is not a viable control
alternative. The v/c ratio for the NBL movement was 3.72, i.e., the volume
was 372% of the capacity. The NBR movement v/c ratio was 1.92.
The WBL movement, on the
other hand, appears to be operating within its capacity, with a v/c ratio of
0.71. This presents an interesting contrast with the NBL movement, since
both movements have to contend with the same conflicting volume (i.e., 2,010
vph from the WBT). The difference may be seen in both the graphical
representation of Exhibit 3-27
and the numerical presentation on
Exhibit 3-.
In the graph, the line representing the WBL shows a much higher capacity for
a given level of opposing volume than the line representing the NBL
movement.
[
Back ] [
Continue ] with Sub-Problem 4b |
Page Break
Home
> Problem 4 >
Sub-problem 4b - Page 4 of 4 Sub-problem 4b:
Two-way Stop Control with
a Normal Urban Intersection Treatment
Exhibit 3-30 explains why
these lines are in different places. The formula for computing the capacity
of a movement that must yield to an opposing movement is given in HCM
equation 17-3. This equation contains two parameters:
-
The critical gap,
which indicates the length of a gap in the opposing flow required to
accommodate the first queued vehicle trying to cross the opposing flow.
-
The follow-up time,
which indicates the additional gap length required to accommodate each
subsequent vehicle entering the same gap in the opposing traffic.
Larger values for each of
these parameters will lower the capacity for the entering movement. The
values shown in Exhibit 3-30 indicate lower values for the left turn crossing
the opposing traffic than for the minor street entry movements. This
indicates that drivers making left turns from the major street are willing
to accept shorter gaps in the opposing traffic than drivers that are
entering the major street from a minor street approach. The result is a
higher capacity for the WBL movement compared to the NBL movement.
Exhibit 3-30. TWSC Analysis
with a Normal Urban Intersection Treatment |
Assumed
Parameters |
Movement |
Input Data |
EBT |
WBT |
NBL |
WBL |
NBR |
Volume (vph) |
2,010 |
358 |
257 |
120 |
433 |
Number of lanes |
2 |
2 |
1 |
1 |
1 |
Median storage
(vehicles) |
N/A |
N/A |
4 |
N/A |
N/A |
Percent trucks |
|
|
20 |
41 |
10 |
Analysis Results |
Critical gap
(sec) |
N/A |
N/A |
7.2 |
4.9 |
7.1 |
Follow up time
(sec) |
N/A |
N/A |
3.7 |
2.6 |
3.4 |
Adjusted flow
rate (vph) |
2010 |
358 |
257 |
120 |
433 |
Adjusted capacity
(vph) |
N/A |
N/A |
69 |
168 |
226 |
v/c ratio |
N/A |
N/A |
3.72 |
0.71 |
1.92 |
95% queue length
(veh) |
N/A |
N/A |
27.1 |
4.4 |
31.1 |
Delay (sev/veh) |
N/A |
N/A |
??? |
67 |
464 |
LOS |
N/A |
N/A |
F |
F |
F |
Simplifying Assumptions
Analysis
period=15 min
No pedestrians
No upstream
signals
PHF = 0.93 for
all movements
Level Terrain |
One of the objectives
of this exercise was to judge whether it is appropriate to consider the
intersection in the context of a normal urban intersection with TWSC
control. This task can be accomplished best by comparing the results in
Exhibit 3-30 with the corresponding results obtained by treating each of the
conflict points separately. We will examine the separation of conflict
points in the next sub-problem. [
Back ] [
Continue ] to Sub-Problem
4c |
Page Break
Home
> Problem 4 >
Sub-problem 4b - Page 5 of 6
Sub-problem 4b: Off-Peak Operational Analysis
of Alternate Route 7
Step 2. Results
Let's first consider the level of service for the facility,
or, more correctly, for each section of the facility that makes up
this analysis. We need to note that, using this method,
there is no overall performance measure for the facility as a whole. Part 3 of the HCM does cover issues relating to corridor and area-wide
analysis. But we will not cover them here. If you are interested
in learning more about this topic, consult part 3 of the HCM.
The level of service for each section is shown in the
table below. Each of the sections performs at level of service C or
better, with the exception of section 2, the weaving section. This
result is consistent with our analysis produced in Problem 2 where we
identified deficiencies with this weaving section during
the peak period. We also noted that, while speeds in other sections
are nearly 50 mph or above, section 2 has a forecasted speed below 28
mph, indicating a problem in the performance of the weaving section.
We can also note that the demand/capacity ratio is near
one for this section. What is the implication of a demand/capacity
ratio that is this high?
SECTION TITLE
(EB Section) |
S01 |
S02 |
S03 |
S04 |
S05 |
S06 |
S07 |
S08 |
S09 |
S10 |
S11 |
Type (B,W, ONR,OFR) |
B |
W |
B |
ONR |
B |
B |
OFR |
B |
ONR |
ONR |
B |
Length (ft) |
3,675 |
670 |
1,025 |
775 |
1,890 |
10,900 |
1,500 |
3,100 |
1,115 |
1,500 |
2,000 |
Number of lanes |
2 |
4 |
2 |
4 |
3 |
2 |
2 |
2 |
2 |
4 |
4 |
Free flow speed (mph) |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
Speed (mph) |
55.0 |
27.9 |
48.1 |
53.4 |
54.8 |
55.0 |
49.9 |
54.9 |
50.8 |
54.5 |
55.0 |
Density (veh/mi/ln) |
10.0 |
35.3 |
7.6 |
10.8 |
14.4 |
21.6 |
21.8 |
13.7 |
17.8 |
15.0 |
14.8 |
Segment Capacity (vph) |
4,375 |
4,100 |
4,375 |
8,750 |
6,565 |
4,375 |
4,375 |
4,375 |
4,375 |
8,750 |
8,750 |
Segment Demand (vph) |
1,095 |
3,930 |
895 |
2,540 |
2,540 |
2,540 |
2,540 |
1,610 |
1,890 |
3,365 |
3,365 |
Segment Volume (vph) |
1,095 |
3,195 |
730 |
2,370 |
2,370 |
2,370 |
2,370 |
1,505 |
1,785 |
3,260 |
3,260 |
d/c ratio |
0.25 |
0.96 |
0.20 |
0.29 |
0.39 |
0.58 |
0.58 |
0.37 |
0.43 |
0.38 |
0.38 |
v/c ratio |
0.25 |
0.78 |
0.17 |
0.27 |
0.36 |
0.54 |
0.54 |
0.34 |
0.41 |
0.37 |
0.37 |
Vehicle LOS |
B |
E |
A |
B |
B |
C |
C |
B |
B |
B |
B |
[
Back ] [
Continue ] with
Sub-problem 4b |
Page Break
Home
> Problem 4
> Sub-problem 4b - Page 6 of 6
Sub-problem 4b: Off-Peak Operational Analysis
of Alternate Route 7
When we examine
the part of the performance table (see below) dealing with ramp operations,
we can see one of the results of the d/c ratio near one for the weaving
section (section 02). Both the demands on the on and off-ramps are not
completely served during this time period. Note for example that the demand
for the on-ramp is 2,835 vehicles, while the actual ramp volume is 2,100
vehicles. But there
are two points to make here that limit the applicability of these results.
First, a limitation in the software used to implement the HCM did not allow
entry of 2 lanes to the on-ramp. This produces an unreasonable result of
ramp delay and queuing. Second, if this limitation was not present and the
results were as shown in the table, the unserved demand during this time
period would be transferred to the next 15-minute time period. The same
caveat must be applied to the off-ramp results. So, while we can learn an
important point about oversaturated conditions (demand exceeds capacity),
this example does have a limitation (due to the software) that we need to
keep in mind. [*team members: do we
want to include a result like this in the guide?*]
|
SECTION
TITLE
(EB SECTION) |
S01 |
S02 |
S03 |
S04 |
S05 |
S06 |
S07 |
S08 |
S09 |
S10 |
S11 |
On-Ramp
Demand (vph) |
|
2,835 |
|
1,645 |
|
|
|
|
280 |
1,470 |
|
On-Ramp
Volume (vph) |
|
2,100 |
|
1,645 |
|
|
|
|
280 |
1,470 |
|
On-Ramp
Delay (veh-hrs of delay) |
|
23 |
|
0 |
|
|
|
|
0 |
0 |
|
On-Ramp
Queue Length (ft) |
|
22,000 |
|
0 |
|
|
|
|
0 |
0 |
|
Off-Ramp
Demand (vph) |
|
3,035 |
|
|
|
|
930 |
|
|
|
|
Off-Ramp
Volume (vph) |
|
2,470 |
|
|
|
|
865 |
|
|
|
|
These results
apply to the off-peak period. In
sub-problem 4c, we will consider the peak
hour operation of the facility.
[
Back ] [
Continue
] with Sub-problem 4b |
Page Break
Home >
Problem 4 >
Sub-problem 4c - Page 1 of 3 Sub-problem 4c: Separating the
Conflict Points for TWSC Control
Step 1.
Setup
Because of the wide
median and the high speed rural type channelization of the right turns, it
could be argued that the Okeechobee road intersection is likely to operate
not as the single urban intersection considered in sub-problem 4a but as
four separate intersections, with each intersection representing one of the
conflict points, as shown in the diagram at the right. The separation of
conflict points will usually give a more optimistic assessment of the
operation than will the aggregation of conflict points into a single
intersection.
Consider:
Discussion:
Take
a few minutes to consider these questions. Click continue when you are
ready to proceed. [
Back ] to Sub-problem 4b [
Continue ] with Sub-Problem 4c |
Page Break
Home
> Problem 4 >
Sub-problem 4c - Page 2 of 3 Sub-problem 4c: Separating the
Conflict Points for TWSC Control
Let's consider the questions from the previous page.
Why would separating conflicts produce a more
optimistic assessment of the intersections?
Separating conflicts may produce a more optimistic assessment, because as
conflicting streams of traffic are removed from consideration, it results in
more opportunities for acceptable gaps. The relationship is exponential and
depending on conditions that may result in significant overestimation of
capacity. For this reason, caution must be used when separating the conflict points for an unsignalized intersection.
How are the conflict points inter-related? The
most obvious relationship between the conflict points is how the paths of
vehicles overlap multiple conflict points. For example, the northbound left-turn movement must pass through two points. Thus, if the second conflict
path (northbound left turn and westbound through) is currently blocked by a
queue of vehicles waiting
for access, the analysis may be invalid. To determine whether the conflict
points at an intersection may be separated, it is necessary to estimate the
queue length for the each of the entering movements. If the estimated queue lengths are greater than
the available storage space, then the separation of conflict points may
overestimate or produce an unrealistic assessment of the operation.
Step 2. Results
Exhibit 3-31
shows the
results of this analysis. In all cases, the movement capacities were
improved in comparison with Sub-problem 4b, which considered all of the
intersection conflicts simultaneously. This would be expected, but the
important question is whether or not the queue backup would exceed the
available storage space, thereby invalidating the analysis. Inspection of
Exhibit 3-31
indicates that the 95th-percentile queue lengths remained well
within the storage boundaries. So, it could be concluded that it is
appropriate to separate the conflict points for this intersection. While the
separation of conflict points improved the operation slightly, some of the
movements remain badly oversaturated—and the earlier conclusion that TWSC
will result in a peak hour deficiency is confirmed.
[
Back ] [
Continue ] with Sub-Problem 4c |
Page Break
Home
> Problem 4 >
Sub-problem 4c - Page 3 of 3 Sub-problem 4c: Separating the
Conflict Points for TWSC Control
One more observation may
be made from Exhibit 3-31. The NB right turn, even with the conflict points
separated, indicates an oversaturated condition when analyzed as
a TWSC operation. Because of the geometrics, the right-turn entry has more
of the characteristics of a merge than a stop-controlled approach. This
should raise some question as to whether another analysis procedure might be
more appropriate. The treatment as a freeway entrance ramp will be
considered in the next sub-problem.
Exhibit 3-31. TWSC Analysis
with Conflict Points Separated |
Input Data |
EBT |
WBT |
NBL |
WBL |
NBR |
Volume |
2,010 |
358 |
257 |
120 |
433 |
Number of lanes |
2 |
2 |
1 |
1 |
1 |
Percent trucks |
|
|
20 |
41 |
10 |
NB Left vs EB Through |
Sub-problem 4b
Capacity |
|
|
69 |
|
|
Sub-problem 4c
Capacity |
--- |
--- |
99 |
--- |
|
95% queue length
(veh) |
--- |
--- |
24 |
--- |
|
Queue storage (veh) |
--- |
--- |
N/A |
--- |
|
Is storage
adequate? |
--- |
--- |
N/A |
--- |
|
v/c ratio |
--- |
--- |
2.6 |
--- |
|
Delay |
--- |
--- |
814 |
--- |
|
LOS |
--- |
--- |
F |
--- |
|
NB Left vs WB Through and
Left |
Sub-problem 4b
Capacity |
|
|
N/A |
|
|
Sub-problem 4c
Capacity |
--- |
--- |
559 |
--- |
|
95% queue length
(veh) |
--- |
--- |
2.4 |
--- |
|
Queue storage (veh) |
--- |
--- |
4 |
--- |
|
Is storage
adequate? |
--- |
--- |
Yes |
--- |
|
v/c ratio |
--- |
--- |
0.46 |
--- |
|
Delay |
--- |
--- |
17 |
--- |
|
LOS |
--- |
--- |
C |
--- |
|
WB Left vs EB Through |
Sub-problem 4b
Capacity |
|
|
|
168 |
|
Sub-problem 4c
Capacity |
--- |
--- |
--- |
213 |
|
95% queue length
(veh) |
--- |
--- |
--- |
2.07 |
|
Queue storage (veh) |
|
--- |
--- |
3.06 |
|
Is storage
adequate? |
|
--- |
--- |
Yes |
|
v/c ratio |
--- |
--- |
--- |
0.56 |
|
Delay |
--- |
--- |
--- |
41.7 |
|
LOS |
--- |
--- |
--- |
E |
|
NB Right vs EB Through |
Sub-problem 4b
Capacity |
|
|
|
|
226 |
Sub-problem 4c
Capacity |
|
|
|
|
283 |
95% queue length
(veh) |
|
|
|
|
25 |
Queue storage (veh) |
|
|
|
|
N/A |
Is storage
adequate? |
|
|
|
|
N/A |
v/c ratio |
|
|
|
|
1.53 |
Delay |
|
|
|
|
287 |
LOS |
|
|
|
|
F |
[
Back ] [
Continue ] to Sub-Problem
4d |
Page Break
Home
> Problem 4 >
Sub-problem 4c - Page 4 of 7
Sub-problem 4c: Peak Operational Analysis of
Alternate Route 7
Let's now consider time period 2, the second 15-minute period
during the PM peak period. The results for time period 2 are shown in the table below. Study the data presented in the table carefully.
Section (Time Period 2) |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
Length (ft) |
3,675 |
670 |
1,025 |
775 |
1,890 |
10,900 |
1,500 |
3,100 |
1,115 |
1,500 |
2,000 |
Number of lanes |
2 |
4 |
2 |
4 |
3 |
2 |
2 |
2 |
2 |
4 |
4 |
Type (B,W, ONR, OFR) |
B |
W |
B |
ONR |
B |
B |
OFR |
B |
ONR |
ONR |
B |
Free flow speed (mph) |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
Speed (mph) |
55.0 |
33.3 |
49.5 |
25.8 |
19.2 |
49.8 |
49.4 |
54.9 |
48.9 |
54.3 |
55.0 |
Density (veh/mi/ln) |
19.5 |
25.7 |
21.2 |
44.9 |
75.8 |
44.0 |
39.4 |
28.4 |
31.3 |
26.1 |
26.2 |
Segment Capacity (vph) |
4,375 |
5,020 |
4,375 |
8,750 |
6,565 |
4,375 |
4,375 |
4,375 |
4,375 |
8,750 |
8,750 |
Segment Demand (vph) |
2,150 |
3,425 |
2,100 |
4,850 |
4,850 |
4,850 |
4,850 |
3,460 |
3,880 |
6,090 |
6,090 |
Segment Volume (vph) |
2,150 |
3,425 |
2,100 |
4,640 |
4,375 |
4,375 |
4,375 |
3,120 |
3,540 |
5,750 |
5,750 |
d/c ratio |
0.49 |
0.68 |
0.48 |
0.55 |
0.74 |
1.11 |
1.11 |
0.79 |
0.89 |
0.70 |
0.70 |
v/c ratio |
0.49 |
0.68 |
0.48 |
0.53 |
0.67 |
1.00 |
1.00 |
0.71 |
0.81 |
0.66 |
0.66 |
Minute Queue Begins in Segment |
|
|
|
9 |
1 |
|
|
|
|
|
|
Minute Queue Ends in Segment |
|
|
|
** |
** |
|
|
|
|
|
|
Queue Length at End of Time Period (ft) |
|
|
|
745 |
1,890 |
|
|
|
|
|
|
Discussion:
As you review the data in the table above, what differences do you see
between these results and those from time period 1? What is the most
important information you learn from this table? When you are ready, proceed to the next page.
[Back] [Continue]
with Sub-problem 4c |
Page Break
Home
> Problem 4 >
Sub-problem 4c - Page 5 of 7
Sub-problem 4c: Peak Operational Analysis of
Alternate Route 7
The main point that we can learn from the table showing
results from time period 2 is that we have a bottleneck,
a point along the freeway facility that limits or constrains the demand.
This bottleneck shows up in section 6, where the volume/capacity ratio
equals one.
What is the cause of this constraint? If we review the line
drawings showing the geometric information for the eastbound portion of
Alternate Route
7, we see that this is where the mainline drops from three lanes to two
lanes. At this point, the demand exceeds the capacity of the two lane
section and a queue begins to build at this point, traveling upstream. At the end of this 15-minute period (time period 2), the queue extends the entire length of
section 5 (1,890 feet). It also reaches section 4 nine minutes after the
beginning of time period 2 and extends 745 feet through this section by the
end of the 15-minute time period.
Both sections operate at level of service F, even though
the demand/capacity ratios for these sections are well below 1.0. Why? These
sections are in the congested regions of the speed/flow diagram (*add
link*), as shown by the very low speeds (below 30 mph) that exist in
these sections.
[Back]
[Continue]
with Sub-problem 4c |
Page Break
Home
> Problem 4
> Sub-problem 4c - Page 6 of 7
Sub-problem 4c: Peak Operational Analysis of
Alternate Route 7
Let's note one
other result for the sections downstream from the bottleneck (section 6).
Note that the volume/capacity ratio is less than the demand/capacity ratio.
Or, similarly, the demand is higher than the volume. What is the implication
of this result? Some vehicles that desire to reach sections
downstream from the bottleneck (sections 7 through 11) are unable to do so
during time period 2. They are in the queue forming in sections 4
and 5 and will be delayed in this queue until at least time period 3. This unserved demand is transferred from time period 2 to time period 3.
Section (Time Period 2) |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
Length (ft) |
3,675 |
670 |
1,025 |
775 |
1,890 |
10,900 |
1,500 |
3,100 |
1,115 |
1,500 |
2,000 |
Number of lanes |
2 |
4 |
2 |
4 |
3 |
2 |
2 |
2 |
2 |
4 |
4 |
Type (B,W, ONR, OFR) |
B |
W |
B |
ONR |
B |
B |
OFR |
B |
ONR |
ONR |
B |
Free flow speed (mph) |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
55 |
Speed (mph) |
55.0 |
33.3 |
49.5 |
25.8 |
19.2 |
49.8 |
49.4 |
54.9 |
48.9 |
54.3 |
55.0 |
Density (veh/mi/ln) |
19.5 |
25.7 |
21.2 |
44.9 |
75.8 |
44.0 |
39.4 |
28.4 |
31.3 |
26.1 |
26.2 |
Segment Capacity (vph) |
4,375 |
5,020 |
4,375 |
8,750 |
6,565 |
4,375 |
4,375 |
4,375 |
4,375 |
8,750 |
8,750 |
Level of Service |
C |
C |
C |
F |
F |
F |
E |
D |
D |
C |
D |
Segment Demand (vph) |
2,150 |
3,425 |
2,100 |
4,850 |
4,850 |
4,850 |
4,850 |
3,460 |
3,880 |
6,090 |
6,090 |
Segment Volume (vph) |
2,150 |
3,425 |
2,100 |
4,640 |
4,375 |
4,375 |
4,375 |
3,120 |
3,540 |
5,750 |
5,750 |
d/c ratio |
0.49 |
0.68 |
0.48 |
0.55 |
0.74 |
1.11 |
1.11 |
0.79 |
0.89 |
0.70 |
0.70 |
v/c ratio |
0.49 |
0.68 |
0.48 |
0.53 |
0.67 |
1.00 |
1.00 |
0.71 |
0.81 |
0.66 |
0.66 |
Minute Queue Begins in Segment |
|
|
|
9 |
1 |
|
|
|
|
|
|
Minute Queue Ends in Segment |
|
|
|
** |
** |
|
|
|
|
|
|
Queue Length at End of Time Period (ft) |
|
|
|
745 |
1,890 |
|
|
|
|
|
|
When you are ready to review the results from time periods
3 and 4, proceed to the next page.
[Back]
[Continue] with Sub-problem 4c |
Page Break
Home
> Problem 4 >
Sub-problem 4c - Page 7 of 7
Sub-problem 4c: Peak Operational Analysis of
Alternate Route 7
The tables below show the results for time periods 3 and 4.
We note in the first table that the queue formed during time period 2 clears
during time period 3, by the first minute in section 3 and by the third
minute in section 5. You can see that the demand that wasn't served during
time period 2 has been transferred to time period 3, since the volumes in
sections 4 through 11 that actually use the facility exceed the original
demand for these sections. For example, in section 5, the volume is 1,745,
while the demand is 1,270. This means that a flow rate of 1,745 minus 1,270,
or 475, has been transferred from time period 2 to time period 3. And since
the demand for time period 3 is low enough, there is sufficient capacity to
serve both the original demand (1,270), plus the transferred demand (475).
During time period 3, all sections operate at level of
service C or better, with the exception of section 5, which is still
recovering from the queue, and operates at level of service E. The
speed in section 5 is less than 20 mph during this recovery.
But by time period 4, all sections of the freeway facility
are operating at LOS B or better. All speeds exceed 40 mi/hr. And, once again, the demand equals the volume, indicating that all vehicles
desiring to travel along the facility during time period 4 are served.
Section (Time period 3) |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
Speed (mph) |
55.0 |
42.5 |
51.8 |
-276.2 |
16.5 |
55.0 |
50.2 |
54.9 |
50.9 |
54.5 |
55.0 |
Density (veh/mi/ln) |
5.0 |
11.6 |
4.3 |
-1.3 |
13.5 |
15.9 |
16.4 |
10.4 |
13.9 |
10.0 |
9.2 |
Segment Capacity (vph) |
4,376 |
5,444 |
4,376 |
8,751 |
6,563 |
4,376 |
4,376 |
4,376 |
4,376 |
8,751 |
8,751 |
Level of Service |
A |
B |
A |
B |
E |
C |
B |
B |
B |
B |
A |
Segment Demand (vph) |
548 |
1,965 |
448 |
1,270 |
1,270 |
1,270 |
1,270 |
806 |
947 |
1,683 |
1,683 |
Segment Volume (vph) |
548 |
1,965 |
448 |
1,479 |
1,744 |
1,744 |
1,744 |
1,144 |
1,285 |
2,021 |
2,021 |
d/c ratio |
0.13 |
0.36 |
0.10 |
0.15 |
0.19 |
0.29 |
0.29 |
0.18 |
0.22 |
0.19 |
0.19 |
v/c ratio |
0.13 |
0.36 |
0.10 |
0.17 |
0.27 |
0.40 |
0.40 |
0.26 |
0.29 |
0.23 |
0.23 |
Minute Queue Begins in Segment |
|
|
|
** |
** |
|
|
|
|
|
|
Minute Queue Ends in Segment |
|
|
|
1 |
3 |
|
|
|
|
|
|
Section (Time period 4) |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
Speed (mph) |
55.0 |
44.7 |
52.4 |
54.4 |
54.9 |
55.0 |
50.5 |
54.9 |
51.0 |
54.5 |
55.0 |
Density (veh/mi/ln) |
4.0 |
8.8 |
3.4 |
5.6 |
6.2 |
9.2 |
10.0 |
5.9 |
9.9 |
7.1 |
6.1 |
Segment Capacity (vph) |
4,376 |
5,448 |
4,376 |
8,751 |
6,563 |
4,376 |
4,376 |
4,376 |
4,376 |
8,751 |
8,751 |
Level of Service |
A |
A |
A |
A |
A |
A |
B |
A |
B |
A |
A |
Segment Demand (vph) |
438 |
1,571 |
357 |
1,015 |
1,015 |
1,015 |
1,015 |
644 |
756 |
1,345 |
1,345 |
Segment Volume (vph) |
438 |
1,571 |
357 |
1,015 |
1,015 |
1,015 |
1,015 |
644 |
756 |
1,345 |
1,345 |
d/c ratio |
0.10 |
0.29 |
0.08 |
0.12 |
0.15 |
0.23 |
0.23 |
0.15 |
0.17 |
0.15 |
0.15 |
v/c ratio |
0.10 |
0.29 |
0.08 |
0.12 |
0.15 |
0.23 |
0.23 |
0.15 |
0.17 |
0.15 |
0.15 |
[Back]
[Continue]
with Analysis |
Page Break
Home
> Problem 4 >
Analysis Problem 4: Analysis
We have now completed a review of the operation of Alternate Route
7 during the PM peak period. The operation of this facility is typical of
many urban freeways during peak periods. At the beginning of the peak, the
facility operates at acceptable levels of service, and all demand is served
during the first 15-minute time period. During the second time period, a
queue begins to form as the demand exceeds the capacity where the
facility drops from three lanes to two. This is a classic freeway
bottleneck condition. The queue extends from the bottleneck point between
sections 5 and 6 (where the lane drop occurs) upstream through section 5 and
into part of section 4. The bottleneck, and the resulting queue, delays
vehicles that entered the system during time period 2 to the next time period. The queue clears during time period 3, and the freeway is back to good operation
during time period 4.
The table below provides a summary of some of the key data for
the four time periods that we have reviewed.
Parameter |
Time period 1 |
Time period 2 |
Time period 3 |
Time period 4 |
Density (veh/mi/lane)
Queueing?
Mainline travel time (min/veh)
Mainline traffic delay (min/veh)
Mainline speed (mi/hr)
Level of service range |
16.4
No
5.88
0.06
54.42
A - C |
36.9
Yes
7.15
1.33
44.15
C - F |
11.3
Yes
6.64
0.82
47.03
A - E |
7.2
No
5.91
0.09
53.96
A - B |
These summary data provide several interesting insights, at a
more system level, on the performance of the freeway facility.
-
Even in time period 1, when there is no queuing, there
is delay. How can this be true? Recall that delay is the time
that a driver spends traveling at less than preferred speed. The average mainline speed is less than 55 mph (54.42 mph), so there is
some, though minimal, delay. The delay increases during time period
2 to nearly 1.5 minutes per vehicle, and the average speed drops to 44.15
mph.
- These system measures do provide a broad perspective on
the performance of the freeway facility and are therefore valuable aids
to analysts and decision makers. However, to understand the
specific causes of delay or queuing, we must always look at the details of
the facility performance, checking the data for each section to understand
the causes of poor performance.
What are the implications of these results? Do we
need to continue with further analysis of this freeway facility? When
you are ready, proceed to the next page.
[Back] to
Sub-problem 4c
[Continue] to Discussion of Problem 4 |
Page Break
Problem 4: Discussion
The freeway facility methodology from chapter 22 of the HCM
has provided us with important insights on the performance of Alternate Route 7
during both the off peak and peak periods. We found the facility
performs well during the off peak, but the lane drop from three to
two lanes on the eastbound portion of the facility results in some delay for
motorists during the PM peak period.
We also need to consider whether further analyses should
be conducted to have a complete picture of the operation of this facility. Let's consider
the following issues:
-
Have we considered a wide enough view of the system?
-
Are there limitations of the HCM methodology that
require us to use other tools, such as simulation?
The system that we considered is the
mainline portion of Alternate
Route 7 from the I-87 interchange on the west to the I-787 interchange on the
east. But do we need to extend the boundary of our study area further in
order to capture any other effects? We know that there are problems with
the interchanges themselves. Some of these problems appeared in the analysis
that we conducted for problems 2 and 3 of this case study. So, widening the
system to include the interchanges might prove beneficial in our assessment of
Alternate Route 7.
This leads to the next issue, the possible use of
micro-simulation. Under what conditions should we consider
micro-simulation modeling? The first such condition is when demand exceeds
capacity, particularly when there is an intersection of queues on the facility. Here,
there is value in the ability of a micro-simulation model to follow the behavior of
individual vehicles and drivers as they negotiate a congested facility. A second such condition is when we are considering a large and complex
system, such as a freeway mainline and interchanges.
In problem 5 of this case study, we will illustrate how one
micro-simulation tool can be used to study the operation of Alternate Route 7.
[
Back
] to Analysis
of Problem 4 [ Continue ] to
Problem 5 |
|