Subproblem 3b - Page 4 of 6

ID# C303B04

Sub-problem 3b: Operational Analysis of the Center Section of Krome Avenue (Class I or II Two-Lane Highway Facility)

Step 2. Results

Exhibit 3-20 compares the results from the planning level analysis in sub-problem 2b with the operational level analysis. It shows the values assumed by the service volume tables for all parameters, as compared with the values that apply to this facility. It also shows the computations and results for both methods. The ATS was computed as 39.3 mph. The PTSF was computed as 70.1%.

If this facility were designated as a Class I highway, the ATS would be the critical determinant of LOS, producing a value of E. The PTSF would have suggested LOS D. If the designation were changed to Class II, the ATS would be eliminated as a determinant of LOS, and the PTSF would establish LOS D.

Exhibit 3-20. Center Section: Comparison of Planning and Operational Level Analysis Results

 

Input Data

Table Assumptions

HCM Chapter 10

Sub-problem 2b

Field Observations

HCM Chapter 20

Sub-problem 3b

Terrain Level Level
Base Free Flow Speed N/A 53.1 mph
Access Points Per Mile N/A 2
Shoulder Width N/A 3
Free Flow Speed 50 mph 50
Directional Split 60/40 57/43
Percent Trucks 14 26
Percent RV's 4 Included in Percent Trucks
Percent No Passing 20 8
PHF N/A 0.91
Design Hour Volume 1,190 1,190
  Comparison of Results
Table Thresholds Computations
LOS A: ---

ATS=39.3

PTSF=70.1

v/c=0.42

LOS B: ---
LOS C: 330
LOS D: 1,000
LOS E: 2,770
Estimated LOS
Class I Facility E E
Class II Facility N/A D