Sub-problem 5b - Page 1 of 7 Sub-problem 5b: Three-Phase Traffic Signal Control with a Protected Westbound Left Turn Step 1. Setup Having established the need for westbound left-turn protection in Sub-problem 5a, we will now examine the HCM treatment of protected left turns. Because of the isolated and high speed characteristics of this intersection, we would expect to implement a control scheme in which all movements are traffic-actuated. We will, however, limit the investigation to pre-timed control in this sub-problem, leaving traffic-actuated control for Sub-problem 5c. There are two reasons to separate the control treatment into different sub-problems. First, we can get a better idea of how these control modes differ if we examine both of them in detail. Second, the timing plan based on pre-timed control is often a useful input into the analysis of traffic-actuated operation. Consider: